The Boston Redevelopment Authority: How Does it Work?

Eleven steps major Boston projects have to complete from proposal to final approval.

If you start with an open hand and close a finger for each time you can recall hearing the Boston Redevelopment Authority's name spoken in scorn, we suspect that you’ll end the exercise with a fist—perhaps a tightly-clenched one.

The agency's rules can frustrate developers and designers, and its decisions often seem arcane and opaque to Charlestown residents.

But the Authority tries to be open, according to Heather Campisano, the authority’s Deputy Director for Development Review. As an example, she outlined in a conversation with Patch how the BRA handles input from the public on projects larger than 50,000 square feet.

Find out what's happening in Charlestownwith free, real-time updates from Patch.

Major steps:

  1. The developer proposes the project.
  2. The BRA distributes the proposal to city agencies.
  3. The developer is encouraged to present the project before community groups. In Charlestown, that would generally be the Charlestown Neighborhood Council.
  4. The project is posted online for a 30-day comment period—To find projects that currently have an open comment period, go to bostonredevelopmentauthority.org and click on the "text" link under the "development" header. Use the drop-down to limit the query to “under review” some (thought not all) of those projects will be in their comment period.
  5. The BRA seeks nominations for an "impact advisory group" composed of interested residents, business owners and representatives of community groups. This group will evaluate how the project negatively impacts the area and suggest ways to mitigate that impact.
  6. The BRA holds "scoping sessions" for the project, where BRA staff and the developer assess how the project is likely to impact the area. The advisory group is encouraged to attend these sessions.
  7. The advisory group makes it recommendations.
  8. Informed by advisory group and public input, BRA staff craft an agreement with the developer.
  9. The project goes before the BRA board of directors in a public hearing.
  10. Should the board approve the project, the advisory group has 15 days to review the final agreement
  11. In some cases, the project goes before the zoning or appeals board for additional public hearings.

To find out about the BRA’s meeting schedule, go to bostonredevelopmentauthority.org and check the “events” box. To keep up with BRA news, go to the authority's blog at bostonredevelopmentauthoritynews.org.

Find out what's happening in Charlestownwith free, real-time updates from Patch.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here

More from Charlestown